|
On May 4th, 2002 at around 11pm a fire broke
out in the D garage of the 7601 building, damaging the C & D units as well
as all the garages.
To this date no cause has been determined.
The fire did start in the garage of the D unit, destroying the vehicle
inside and making the garages unsafe and the D unit inhabitable. There have
been many different theories on what caused the fire but the fire dept
investigators were unable to make a determination on the exact cause.
We do know that the garage was left open all
day. This may or may not have played a factor in the fire. But if the garage
was closed like it should have been then no one could have done anything to
start a fire by getting into the garage as it has been suggested by some.
This is yet another reason we are so strict on the rule of keeping garage
doors shut when no one is present.
The first estimate is in and the total for
repairs is estimated at costing $167,090.82. Needless to say because no one
cause could be deemed, we had to file a claim with the association
insurance company. This in turn caused our insurance premium to raised to
$53,000 a year. What does this mean for you as a resident. Well when
association costs increase so do your association fees. So it is in your
best interest to follow the rules and be as safe as possible. A fire in one
building can and does effect us all.
But There is positives to this event. No one
was hurt or killed. And now the 7601 building will be the building with the
newest siding and best looking.
Below is a time line of progress
March 2nd 2003
One last step!
Everything is now done with the exception of the gutters!
It took a long time, but the end of construction is here and the unit owners
will be moving back in this week!
Check out the Photos
page for Picture of the progress and the new Before & After photos.
Feb 22nd, 2003
Almost done
The C unit is nearly complete, the D unit is very close as well.
Painting and the siding is almost done too! If all goes well, by the end of
next week, the 28th, everything should be finished and unit owners can move
back in.
Feb 14th, 2003
Painting......
All taping, mudding, and sanding is finished on the drywall and primer coat
has been applied.
Some cabinets and doors have also been hung as well as some of the siding on
the building.
Wont be long now till it is finished.
Feb 8th, 2003
Tape and mud
With all the drywall hung, and the inspection of the screws finished, the
process of doing all the taping and mudding has begun!
Feb 5th, 2003
All drywall is up!!
All the drywall is up, and fastener inspection by the village is complete.
Mudding and taping has now started.
Feb 3rd, 2003
Yet closer still!
Drywall is ready for tape and mud in the D unit. Painting of the garage
interiors is started, insulation is almost done on the outside of the
building.
You can see video of this point by
clicking here.
Jan 29th, 2003
Getting closer.
More drywall has been put up and insulation has been installed.
Jan 22nd, 2003
Work is flowing now..
ALL the windows for the C & D units are installed. Ductwork and Drywall have
been started and furnaces installed.
Jan 15th, 2003
A view outside.
The windows for the C & D units have started to be installed. Once these are
done, and the weather warms up, they should be able to start on the siding,
gutters and shutters.
Jan 6th, 2003
Still more progress
Drywall has been installed in the garages of the building and sealing of the
framework is done as well.
We have run into a small snag with a plumbing issue which has set the
completion back to February. Seams the village has decided that even though
the plumbing is exposed that the joints must all be redone. Even though
there was no damage to the plumbing from the fire at all. The village wants
the joints redone because back in 1972 the copper pipes were joined together
with lead. Now even so, the amount of lead used is not nearly close to the
amount that can cause any heath problems.
Barring any more setbacks, the building should be done then.
The building will be getting all new siding, shutters and gutters are well
once the windows are installed.
Nov 26th, 2002
Even more progress
Well With the snow comes a slight slow down in the work. But, all the old
siding has been removed and new Tyvek installed from the garage, and the D &
E units, as well as the side of the B & E units above the ranch units.
Replacement windows for those damaged are ordered, and so have the garage
doors.
Work will continue on the outside until it is finished
before interior work starts. After all it is winter.
If all goes well, and baring any unforeseen problems, work
should be done by Mid January.
Nov 19th, 2002
More progress
Today the new new roof trusses for the garage were finished being installed,
eave on side of garage rebuilt and wood and tar paper installed on the front
of the garage roof.
The damaged studs between the garages and units were also
replaced. as well as part of the wall between the units and garages and the
exterior wall by the garage doors.
Nov 18th, 2002
7601 update
Today the damaged roof trusses on the garage were removed and new ones have
started to be installed. By Tuesday they should be done with them and can
start to lay down the roofing over them.
Nov 15th, 2002
FINALLY!!
The Siding on the garage has been removed and the garage windows have been
removed.
The windows on the garage will not be replaced. This has been done to reduce
maintenance on the buildings and to give them a cleaner look.
The openings were the windows were have been framed in and Tyvek has been
put up on the side walls of the garage.
Nov 14th, 2002
FINALLY!!
The plans have been approved and it looks like the work to rebuild 7601 will
be starting in the next week. It is a pain staking process of getting
drawings done, approved and ok'ed. But its done now and the building can
start. Stay tuned for photos of the progress.
CLICK HERE for photos
|